Webb Dock

Return to projects page


The Webb Dock project (Port of Melbourne) consisted in providing increased capacity for the container trade. To respond to the need of ground improvement underneath the asphalt area (20,000m2), Menard Oceania was awarded the installation of approximately 5,500 CMC, of 360 to 420mm diameter and 9 to 21m deep. Approximately 85, 000lm were drilled in less than 5 months.

Techniques: CMC Rigid Inclusions

Need help with your next project? Contact us today

Contact one of our Experts today

No Comments

Sorry, the comment form is closed at this time.