Webb Dock

Menard Oceania webb dock project initial phase
Return to projects page
Menard Oceania webb dock project initial phase

2014

The Webb Dock project (Port of Melbourne) consisted in providing increased capacity for the container trade. To respond to the need of ground improvement underneath the asphalt area (20,000m2), Menard Oceania was awarded the installation of approximately 5,500 CMC, of 360 to 420mm diameter and 9 to 21m deep. Approximately 85, 000lm were drilled in less than 5 months.

Techniques: CMC Rigid Inclusions