2015
For this project in NSW, it was identified that the cut area for the pond base and embankment foundation will be in weathered rock which potentially could be highly permeable. Consequently, Menard Oceania was engaged to minimize seepage and to provide an effective cut-off of groundwater through the rock. Over the course of project, we completed some 2,200lm of drilling and pressure injected in excess of 64,000L of grout over 300m long grout curtain.
Techniques: Grouting